Subdivision Development Permit

SECURING CERTIFICATE OF ZONING CLEARANCE FOR BUILDING PERMIT

About the Service: Applicants for Building Permit are required to secure a Certificate of Zoning Clearance from the City Planning & Development Office to ensure compatibility or conformity of the project with the existing Land Use Plan of the city, in accordance with City Zoning Ordinance No. 149, series 2000.

Requirement(s):

General:                                    Additional:                               

Application Form                         DAR Clearance

Proof of Land Ownership              Industrial Project Requirements

Vicinity Map                               Special Project Requirements

Site Development Plan                Notarized Authority from Owner if Filed by

Floor Plan and Elevations                   another party

Zoning Certification                     Environmental Compliance Certificate or

Bill of Materials /Project Cost       Certificate of Non-Coverage (ECC/CNC)

Barangay Clearance

How to Avail of the Service?

FOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH
1.  Submit application form and complete requirements to the CPDO Land Use and Zoning Administration Division5 minutesZoning Division Personnel
2.  Wait for field inspection result or accompany zoning inspector during inspection.2 hours (longer if outside the urban area)Zoning Division Personnel
3.  Go to CTO to pay Zoning Clearance Fee and Inspection Fee.approx. 30 minutes (depending on the queue at the CTO)CTO Personnel
4.  Return to CPDO to present receipt and claim approved Zoning Clearance Certificate.10 minutesZoning Division Personnel

For Non-Conforming or Denied Applications

Applicant may opt to file an appeal with the City Zoning Board of Adjustment and Appeals and take the following the steps:

FOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH
1.  Submit Letter of Appeal to the CPDO Land Use and Zoning Administration Division5 minutesZoning Division Personnel
2.  Secure schedule or time table of the action on the appeal by the Zoning Board     Note: Zoning Board action is usually delivered within the prescribed 15-day response time2 minutesZoning Division Personnel
3.  Claim decision of the Zoning Board and Zoning Clearance granted on Variance or Exception     Note: Issuance of Zoning Clearance as Variance is approved by the City Mayor

 SECURING CERTIFICATE OF ZONING CLASSIFICATION

About the Service: Real property owners of titled lots may secure a certificate of zoning classification for various purposes that such may serve them.

Requirement(s):

   Request form/letter

   Vicinity Map

   Lot Plan

   Proof of Land Ownership

   Payment for Inspection Fee

   Payment for Certification Fee

How to Avail of the Service?

FOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH
1.  Go to the CPDO Land Use and Zoning Administration Division, fill up request form and submit all requirements.5 minutesZoning Division Personnel
2.  Wait for field inspection result or accompany zoning inspector during inspection.2 hours (longer if outside the urban area)Zoning Division Personnel
3.  Go to CTO to pay Zoning Certification Fee and Inspection Fee.approx. 30 minutes (depending on the queue at the CTO)CTO Personnel
4.  Return to CPDO to present receipt and claim Zoning Classification Certificate.10 minutesZoning Division Personnel

 4. SECURING CERTIFICATE OF NON-CONFORMANCE FOR BUSINESS PERMIT

About the Service: In line with the devolved functions from the Housing and Land Use Regulatory Board (HLURB) and the City Zoning Ordinance, the CPDO through the Land Use and Zoning Administration Division also issues Certificate of Non-Conformance for existing business establishments whose activity do not conform with the approved land use zone.

Requirement(s):

   Request letter

   Notice of Non-Conformance

   Proof of Land Ownership

   As-built Plan of Project

   Vicinity Map

How to Avail of the Service?

FOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH
1.  Go to the CPDO Land Use and Zoning Administration Division and submit all requirements.5 minutesZoning Division Personnel
2.  Wait for field inspection result or accompany zoning inspector during inspection.2 hours (longer if outside the urban area)Zoning Division Personnel
3.  Go to CTO to pay Zoning Certification Fee and Inspection Fee.approx. 30 minutes (depending on the queue at the CTO)CTO Personnel
4.  Return to CPDO to present receipt and claim approved Certificate of Non-Conformance.10 minutesZoning Division Personnel

 5. SECURING SIMPLE SUBDIVISION APPROVAL

About the Service: In line with the devolved functions from the Housing and Land Use Regulatory Board (HLURB) and the City Zoning Ordinance, the City Government has the mandate to process and approve subdivision projects.

Requirement(s):

   Application Form

   Three (3) sets of the following duly signed and sealed by a licensed Architect/Engineer:

o  Site Development Plan

o  Vicinity Map or Location Plan

   Proof of Land Ownership

   Certification from CEO/CPDO

   Tax Declaration and current tax receipt

   Payment for Simple Division Fee

   Payment for Inspection Fee

How to Avail of the Service?

FOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH
1.  Go to the CPDO Land Use and Zoning Administration Division and submit application form with complete requirements.5 minutesZoning Division Personnel
2.  Wait for documents to be evaluated and secure schedule of inspection.1 dayZoning Division Personnel
3.  Return to CPDO, get advice for payment and go to CTO to pay Simple Subdivision Fee and Inspection Fee.approx. 30 minutes (depending on the queue at the CTO)CTO Personnel
4.  Secure schedule of release from CPDO while documents will be forwarded to the Sangguniang Panlungsod for review and approval.1-2 weeksZoning Division Personnel
5.  Claim approved application for Simple Subdivision.5 minutesZoning Division Personnel

 SECURING PRELIMINARY SUBDIVISION DEVELOPMENT PLAN APPROVAL (PSDP)

About the Service: In line with the devolved functions from the Housing and Land Use Regulatory Board (HLURB) and the City Zoning Ordinance, the City Government has the mandate to process and approve subdivision projects.

Requirement(s):

   Application Form

   Three (3) sets of Site Development Plan duly signed and sealed by a licensed Architect/Engineer

   Vicinity Map signed and sealed by a licensed Geodetic Engineer

   Topographic Plan signed and sealed by a licensed Geodetic Engineer

   Survey plan of the lot based on the TCT signed and sealed by a licensed Geodetic Engineer

   Two (2) copies of Certified True Copy of Title(s) and current Tax Receipts

   Right to use or Deed of Sale of Right-of-Way for access road and other utilities if applicable

   Payment for PSDP

   Payment for Inspection Fee

Fee(s):

Inspection Fee – P 100.00

PSDP Fee – fee(s) vary depending on the area of development

How to Avail of the Service?

FOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH
1.  Go to the CPDO Land Use and Zoning Administration Division and submit application form with complete requirements.5 minutesZoning Division Personnel
2.  Wait for documents to be evaluated and secure schedule of inspection.1 dayZoning Division Personnel
3.  Return to CPDO, get advice for payment and go to CTO to pay PSDP Fee and Inspection Fee.approx. 30 minutes (depending on the queue at the CTO)CTO Personnel
4.  Secure schedule of release from CPDO while documents will be forwarded to the Sangguniang Panlungsod for review and approval.1-2 weeksZoning Division Personnel
5.  Claim approved application for Preliminary Subdivision Development Plan.5 minutesZoning Division Personnel

  SECURING SUBDIVISION DEVELOPMENT PERMIT

About the Service: In line with the devolved functions from the Housing and Land Use Regulatory Board (HLURB) and the City Zoning Ordinance, the City Government has the mandate to process and approve subdivision projects.

Requirement(s):

   Application Form

   All requirements for PSDP

   Subdivision Development Plan

   Civil and Sanitary Works Design

   Two (2) copies of water system layout and details

   Certified true copy of tax declaration

   Zoning Certification from HLURB Regional Office

   Certified true copy of DAR Conversion Order (if applicable)

   Environmental Compliance Certificate or Certificate or Non-Coverage

   Two (2) copies of Project Description

   Plan specifications, bill of materials and cost estimates

   Application for permit to drill from the National Water Resources Board (NWRB) if applicable

   Traffic impact assessment for projects covering 30 hectares and above

   List of Names of duly licensed professionals who signed the plans

   Payment for Subdisision Development Permit

   Payment for Inspection Fee

How to Avail of the Service?

FOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH
1.  Go to the CPDO Land Use and Zoning Administration Division and submit application form with complete requirements.5 minutesZoning Division Personnel
2.  Wait for documents to be evaluated and secure schedule of inspection.1 dayZoning Division Personnel
3.  Return to CPDO, get advice for payment and go to CTO to pay Subdivision Development Permit Fee and Inspection Fee.approx. 30 minutes (depending on the queue at the CTO)CTO Personnel
4.  Secure schedule of release from CPDO while documents will be forwarded to the CEO for engineering review and technical evaluation and to the City Mayor for approval.10 daysZoning Division Personnel
5.  Claim approved Subdivision Development Permit.5 minutesZoning Division Personnel

 8. SECURING APPROVAL FOR ALTERATION OF SUBDIVISION PLAN

About the service: In line with the devolved functions from the Housing and Land Use Regulatory Board (HLURB) and the City Zoning Ordinance, the City Government has the mandate to process and approve subdivision projects and related activities. Previously approved subdivision plans may apply for alteration whenever it is deemed fit.

Requirement(s):

1. Application Form

2. Four (4) copies of the Plan showing the proposed alteration

3. Letter stating the proposed or reason for the proposed alteration or conversion

4. Sworn statement that the affected lots or units for alteration have not been sold

5. Written conformity of the duly organized homeowners association or in the absence thereof, majority of the lot/units buyers, if applicable

6. Certified true copy of title(s) of the affected lots/units if applicable

How to Avail of the Service?

FOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH
1.  Go to the CPDO Land Use and Zoning Administration Division and submit application form with complete requirements.5 minutesZoning Division Personnel
2.  Wait for documents to be evaluated.1 dayZoning Division Personnel
3.  Return to CPDO, get advice for payment and go to CTO to pay corresponding fee.approx. 30 minutes (depending on the queue at the CTO)CTO Personnel
4.  Secure schedule of release from CPDO while documents will be forwarded to the Sangguniang Panlungsod for review and approval.1-2 weeksZoning Division Personnel
5.  Claim approved application for revised Subdivision Development Plan.